Project Overview

The multi-phase University Hospital, San Antonio Downtown Campus project is part of the University Health System - Capital Improvement Program Mission-Target 2012 We look forward to building the UHCD for our community.

Improvements:

  • New clinical services building
  • New diagnostic and treatment equipment
  • Site improvements
  • Renovate and demolish existing buildings

Sub/Supplier Estimating & Procurement Schedule
Tentative CSP Date:

  • MEP Design Assist Complete
  • Package 1: W. Annex, Bldg “B” Demo / W. Annex & North Parking Lot April 29, 2010
  • Package 2: Clinical Services Building
  • Package 2.1: Sitework, Piers, Site Utilities and U/G MEP November 4, 2010
  • Package 2.2: Building Superstructure. January 18, 2011
  • Package 2.3: Exterior & Interior Architectural & MEP. April 2011
  • Package 3: Remodeling Bldg A&C, Parking Lot “B” & Acillary Campus Work. May 2011
  • Package 4: Crisis Care Center – Building & Sitework. July 2011
*Subject to change