The multi-phase University Hospital, San Antonio Downtown Campus project is part of the University Health System - Capital Improvement Program Mission-Target 2012 We look forward to building the UHCD for our community.
Improvements:
- New clinical services building
- New diagnostic and treatment equipment
- Site improvements
- Renovate and demolish existing buildings
Sub/Supplier Estimating & Procurement Schedule Tentative CSP Date:
- MEP Design Assist Complete
- Package 1: W. Annex, Bldg “B” Demo / W. Annex & North Parking Lot April 29, 2010
- Package 2: Clinical Services Building
- Package 2.1: Sitework, Piers, Site Utilities and U/G MEP November 4, 2010
- Package 2.2: Building Superstructure. January 18, 2011
- Package 2.3: Exterior & Interior Architectural & MEP. April 2011
- Package 3: Remodeling Bldg A&C, Parking Lot “B” & Acillary Campus Work. May 2011
- Package 4: Crisis Care Center – Building & Sitework. July 2011
*Subject to change |
|
|